Objectives
  • Create a scenic waterfront for leisure and tourism.

  • Support local hospitality ventures such as restaurants, gardens, and event spaces.

  • Enhance climate resilience by introducing a sustainable water body in a dry corridor.

Key Features
  • Artificial lake constructed with a compact clay base and natural inflow channels.

  • Landscaped lakefront with shaded trees, walkways, and picnic lawns.

  • Provision for boat rides, events, and eco-tourism activities.

  • Integrated stormwater harvesting system to replenish the lake during dry seasons.

Impact

Mubende Resort Beach has become a popular weekend escape and a source of local employment. The project promotes eco-tourism and recreation while serving as a demonstration site for sustainable lake construction in Uganda’s cattle corridor.

Eco-Lakes (1)
Eco-Lakes International (10)

Artificial Lake Establishment Cost Estimates

Component Item Description Unit Qty Unit Cost (UGX) Total Cost (UGX) Remarks
1. Feasibility & Design Feasibility Study & Environmental Impact Assessment (EIA) Lump Sum 1 5,000,000 5,000,000 Includes site surveys, EIA, consultations
1. Feasibility & Design Topographic & Hydrogeological Survey Acre 2 1,500,000 3,000,000 Drone/GPS + soil & water table tests
Feasibility & Design Engineering Design & Drawings Lump Sum 1 4,000,000 4,000,000 Detailed designs with CAD output
2. Site Preparation & Earthworks Site clearing and bush removal Acre 2 1,000,000 2,000,000 Manual/mechanical clearing
Site Preparation & Earthworks Excavation and basin shaping 2,000 12,000 24,000,000 Depth and contour-based costing
Site Preparation & Earthworks Embankment construction 800 15,000 12,000,000 Using excavated or imported soil
Site Preparation & Earthworks Compaction of lake bed and embankments 5,000 3,000 15,000,000 Compacted with rollers
3. Lining & Sealing Clay lining (imported/local) 1,000 20,000 20,000,000 If soil is not clay-rich
4. Water Supply & Inlets Intake structures (gravity-fed) Lump Sum 1 5,000,000 5,000,000 Canals or pipes
Water Supply & Inlets Water pumping system (solar powered) Set 1 15,000,000 15,000,000 Optional backup system
5. Drainage & Control Structures Spillway (stone masonry) m 20 100,000 2,000,000 Overflow control
Drainage & Control Structures Outlet pipes and culverts m 30 80,000 2,400,000 Controlled water release
Drainage & Control Structures Silt traps & sediment basins No. 2 1,500,000 3,000,000 Protect lake lifespan
Sub Total 112,400,000